1, the fixed conveyor installation method should be required to install a fixed basis. Mobile conveyor official before running wheels should live or with a triangular wedge

brakes stopped. Avoid walking around the work place, a number of gravity conveyor parallel operation, the machine and the machine between the machine and the wall between

Channels should have a meter.
2, the conveyor must be inspected prior to use part of the operation, the tape fastener and bearing device is normal, protective equipment is complete. Tape tension must be

adjusted to fit before the start of the degree.
3, belt conveyor should load start. Other operating normally before feeding. Prohibits driving after the first feeding.
4, several conveyor running series, we should begin the discharge end, the sequence starts. All normal operation only after the feeding.
5, run the tape deviation phenomenon occurs, you should stop adjustment shall not be reluctant to use, so as not to wear edges and increase the load.
6, the working environment and sent the material temperature not higher than 50 ℃ and below -10 ℃.
7, the conveyor belt prohibit pedestrians or by people.
8, must be stopped before stopping feeding, unloading and other material on the belt to make deposits before parking.
9, the conveyor motor must be well insulated. roller conveyor cables do not Luanla and dragging. Motor must be grounded reliably.
10, belt slipping a hand to pull the belt is strictly prohibited, so as to avoid accidents.